The council has got in contact with more information including timescales and specific road closures in connection with the SSE power cable installation roadworks – currently causing disruption on the Wokingham Road. More information below. Let us know how this goes and we will keep up the pressure for it to be done as quickly as possible.
If you have any questions contact Luke Massey at the council Luke.massey@reading.gov.uk if you are struggling to get an answer email me rob@readinggreenparty.org.uk
The council says:
"SSE are in the process of laying a new 33khw cable to increase the power supply to Readings Network/substations due to the current supply nearing capacity. The works began outside of Reading Borough (Wokingham Borough from A4 London Road) and will ultimately end at Northumberland Avenue/Cressingham Road sub-station. Due to the location of existing services within the carriageways, and the required space to direct the substantial cables along a suitable route, SSE has considered it necessary to close some streets for safety reasons while the works are carried out.
The works have been taking place on Wokingham Road under temporary traffic signals while ducting is laid between Palmer Park Avenue and Crescent Road. This phase of these works is due to be completed by SSE on 21st July, then to progress along Crescent Road under their full road closure until 1st September (throughout the School Holidays to minimise disruption to the schools within this Street).
SSE have committed to issuing a press release and to conducting a letter drop to affected properties prior to the works beginning here. They have provided the below programme of works, but please note this is subject to change dependant on any unforeseen engineering difficulties that they may encounter. SSE’s manager for this project has offered to host a meeting with local councillors to discuss the works in detail should you wish and will keep us updated on any significant developments.
Road Name
|
Area
|
Guide Dates
|
Traffic Management
|
Wokingham Road
|
Between Crescent Road and entrance to Palmer Park
|
17/06/19 – 21/07/19
|
Traffic Signals
|
Crescent Road
|
Between Wokingham Road and Addington Road
|
21/07/19 – 02/09/19
|
Road Closure
|
Cressingham Road
|
Between roundabout with Northumberland Avenue and Shinfield Road
|
05/09/19 – 26/10/19
|
Traffic Signals
|
Addington Road
|
Between Crescent Road and Alexandra Road
|
02/09/19 – 20/09/19
|
Road Closure
|
Alexandra Road
|
Between Addington Road and Upper Redlands Road
|
20/09/19 – 04/10/19
|
Road Closure
|
Upper Redlands Road
|
Crossing between Alexandra Road and Elmhurst Road
|
04/10/19 – 14/10/19
|
Traffic Signals
|
Shinfield Road
|
Between Cressingham Road and Elmhurst Road
|
26/10/19 – 21/12/19
|
Traffic Signals
|
A4 London Road
|
Between entrance to Palmer Park and Roundabout with A3290
|
14/10/19 – 03/11/19
|
Traffic Signals
|
A4 London Road
|
Across roundabout with A3290 to near Aisha Masjid & Islamic Centre
|
03/11/19 – 05/12/19
|
Lane Closures
|
Elmhurst Road
|
Between Upper Redlands Road and Shinfield Road
|
06/01/20 – 28/01/20
|
Closure
|
Northumberland Avenue
|
Between existing substation across roundabout into Cressingham Road
|
06/01/20 – 11/01/20
|
Traffic Signals
|
Palmer Park
|
Works within park land between Wokingham Road and London Road
|
TBC
|
TBC
|