Thursday, 11 July 2019

East Reading power cable roadworks - road closures and lights


The council has got in contact with more information including timescales and specific road closures in connection with the SSE power cable installation roadworks – currently causing disruption on the Wokingham Road. More information below. Let us know how this goes and we will keep up the pressure for it to be done as quickly as possible.

If you have any questions contact Luke Massey at the council Luke.massey@reading.gov.uk if you are struggling to get an answer email me rob@readinggreenparty.org.uk

The council says:

"SSE are in the process of laying a new 33khw cable to increase the power supply to Readings Network/substations due to the current supply nearing capacity. The works began outside of Reading Borough (Wokingham Borough from A4 London Road) and will ultimately end at Northumberland Avenue/Cressingham Road sub-station. Due to the location of existing services within the carriageways, and the required space to direct the substantial cables along a suitable route, SSE has considered it necessary to close some streets for safety reasons while the works are carried out.

The works have been taking place on Wokingham Road under temporary traffic signals while ducting is laid between Palmer Park Avenue and Crescent Road. This phase of these works is due to be completed by SSE on 21st July, then to progress along Crescent Road under their full road closure until 1st September (throughout the School Holidays to minimise disruption to the schools within this Street).

SSE have committed to issuing a press release and to conducting a letter drop to affected properties prior to the works beginning here. They have provided the below programme of works, but please note this is subject to change dependant on any unforeseen engineering difficulties that they may encounter. SSE’s manager for this project has offered to host a meeting with local councillors to discuss the works in detail should you wish and will keep us updated on any significant developments.

Road Name
Area
Guide Dates
Traffic Management
Wokingham Road
Between Crescent Road and entrance to Palmer Park
17/06/19 – 21/07/19
Traffic Signals
Crescent Road
Between Wokingham Road and Addington Road
21/07/19 – 02/09/19
Road Closure
Cressingham Road
Between roundabout with Northumberland Avenue and Shinfield Road
05/09/19 – 26/10/19
Traffic Signals
Addington Road
Between Crescent Road and Alexandra Road
02/09/19 – 20/09/19
Road Closure
Alexandra Road
Between Addington Road and Upper Redlands Road
20/09/19 – 04/10/19
Road Closure
Upper Redlands Road
Crossing between Alexandra Road and Elmhurst Road
04/10/19 – 14/10/19
Traffic Signals
Shinfield Road
Between Cressingham Road and Elmhurst Road
26/10/19 – 21/12/19
Traffic Signals
A4 London Road
Between entrance to Palmer Park and Roundabout with A3290
14/10/19 – 03/11/19
Traffic Signals
A4 London Road
Across roundabout with A3290 to near Aisha Masjid & Islamic Centre
03/11/19 – 05/12/19
Lane Closures
Elmhurst Road
Between Upper Redlands Road and Shinfield Road
06/01/20 – 28/01/20
Closure
Northumberland Avenue
Between existing substation across roundabout into Cressingham Road
06/01/20 – 11/01/20
Traffic Signals
Palmer Park
Works within park land between Wokingham Road and London Road
TBC
TBC

Wednesday, 3 July 2019

Wokingham Road #rdg roadworks


We have got more information through on the Wokingham Road roadworks. We are still trying to get a better idea on the timescale for these works. We will keep pushing for them to be over as soon as possible.

"Thank you Councillor, for raising your concerns regarding disruption caused by Roadworks  on Wokingham Road. We wish to clarify the works currently in progress are not related to the National Cycle Network which will follow later this year.  The works in progress are part of planned major works being carried out by SSE for the installation of a new 33khw cable being installed along the A4 corridor. The cable enters Reading Borough on London Road under the Network Rail Bridge, adjacent to the A3290.

At this juncture the cable will be divided into two, running in opposite directions; parallel to the rail line, towards the Tesco store, Napier Road and Vastern Road to connect in to the SSE sub-station. The other cable will cut across the back of Palmer Park and parallel to Palmer Park Avenue, exiting on Wokingham Road, leading into Crescent Road, Alexandra Road Elmhurst Road, Shinfield Road, Cressingham and down to Northumberland Avenue to feed in to SSE sub-station.

To help minimise disruption to Road Users in Wokingham Road these works have been planned under temporary traffic signals and allow for continuous use by Road Users. In comparison other sections of the works are planned with road closures and reduced lane availability in consideration of the timing of works during school term times or Summer holidays around Crescent Road Alexandra and Elmhurst Road. 

We are in frequent contact with SSE and the works are being closely monitored to ensure the works are being completed in a safe and timely manner. 

Should you Councillor, or your Constituent wish to discuss the works further directly with SSE we have been advised they would be happy to explain their works and we would be happy to arrange contact.

Please feel equally welcome to direct any further enquiries regarding these works through myself within the StreetWorks Team."