Wednesday 13 June 2012

Bridges Hall update meeting #rdg

I attended the Bridges Hall development update meeting this afternoon. Reading Council had objected to this planning application, but unfortunately Wokingham granted it.

At the meeting there was a reasonable amount of information on how the development will be carried out. Unfortunately this isn't online at the moment, but I asked that it be put there. Here is some information from the meeting.

Building will commence in July 2012 and will be finished by August 2014.

The main contractor is Brookfield Multiplex and the single point of contact for residents who have issues is Ron Allen: ron.allen@upp-ltd.com 07802 688 5469.

They had a fairly long list of measures that they will take to reduce the impact of this development on residents – dust, light, noise etc – but I guess we will have to wait and see as the proof will be in the making of the pudding!

Please get in contact and let me know how things are going.